Enviro Installation

Erection Sequence

1)
Mark out position of partition layout on floor using a chalk line between set points.

Mark corridor runs first, then work back to walls.

If fixed to underside of suspended ceiling or structural ceiling, mark out on ceiling then plumb down to floor and mark out on floor.

2)
Fix "Floor track" to floor, "Wall channel" to walls and "Head track" to structural ceiling, (floor to ceiling), with 6mm hammer fixings, (HF) at approximately 500mm centres. If fixing to steel work use self drill, self tap screws, (SDST) at approximately 500mm centres.

Leave gap in floor track of doorframe module + 4mm for all doorways.
Head track corners and Floor track corners are factory made and connected to straight lengths with a splice. Straight lengths similarly connect to each other with a splice.

3)
Lift panels into position into "Floor base channel". (If fixed at head, lift panels into head then over "Floor base channel" then down). Position panels and doorframes as required. "Door frame fixing bracket" is fixed to floor as per Dwg No. ENV-DFFB using HF or SDST depending on floor construction.

Each panel is levelled by the use of shims as required.

Panels and doorframes are connected together using steel "Roll formed joint section".

4)
90º and 135º, three and four-way panels are fitted as per standard panel modules.

5)
At "Wall channels" where a full panel is being used, insert panel into "Wall channel".

6)
At "Wall channels" where a cut panel is being used, measure the gap, mark the panel and carefully cut. Fit "Cut panel joint channel" (CPJC) to panel and insert cut edge into "Wall channel".

7)
Fit door leaves to doorframes and fit all furniture.

8)
Measure and fit glass of required type into prepared openings.


9)
Apply silicone / polyurethane seal to all joints. (Panel to panel, panel to doorframe etc).

10)
Touch up any damaged paintwork and clean glass and partitions.

11)
Clean site.

12)
Fill in any necessary documentation including obtaining customer approval.