METHOD OF BUILD STATEMENT

Labline Installation

1)
Mark out position of partition layout on floor using a chalk line between set points.

Mark corridor runs first, then work back to walls.

If fixed to underside of suspended ceiling or structural ceiling, mark out on ceiling then plumb down to floor and mark out on floor.

2)
Fix "Floor track" to floor, "Wall channel" to walls and "Head track" to structural ceiling, (floor to ceiling), with 6mm hammer fixings, (HF) at approximately 500mm centres. If fixing to steel work use self drill, self tap screws, (SDST) at approximately 500mm centres.

Leave 950mm gap for single doorways or 1950mm gap for double doorways. No connecting splices are used.

Head track corners and Floor track corners are factory made and connected to straight lengths with a splice. Straight lengths similarly connect to each other with a splice.

3)
Lift panels into position into "Floor base channel". (If fixed at head, lift panels into head then over "Floor base channel" then down). Position panels and doorframes as required. "Door frame angle bracket" is fixed to floor with HF or SDST depending on floor construction.

Each panel is levelled by the use of shims as required.

Panels and doorframes are connected together using "Spacer and connector keys", (SCK3) at approximately 400mm pitch. Pack joints if required, (all fire-rated and acoustic partitions), with mineral wool, then friction fit "Pilasters" (PL2) to all joints.

4)
90º and 135º, three and four-way panels are fitted as per standard panel modules.

5)
At "Wall channels" where a full panel is being used, fit "Wall channel angles" (WCA) to the panel edge and insert panel into "Wall channel".

6)
At "Wall channels" where a cut panel is being used, measure the gap, mark the panel and carefully cut. Fit "Filler channel inner" (FCI) to cut edge and insert panel into "Wall channel"

7)
Fit door leaves to doorframes and fit all furniture.

8)
Measure and fit glass of required type into prepared openings.


9)
Touch up any damaged paintwork and clean glass and partitions.

10)
Clean site.

11)
Fill in any necessary documentation including obtaining customer approval.